how do you find the mean completion time of a PERT network diagram?​

Respuesta :

okekesarah01642112
okekesarah01642112 okekesarah01642112
  • 02-01-2021

Answer:

PERT is an estimating technique that uses a weighted average of three numbers (see below) to come up with a final estimate. The resulting PERT estimate is calculated as (O + 4M + P)/6. This is called a "weighted average" since the most likely estimate is weighted four times as much as the other two values.

Answer Link

Otras preguntas

The United States gained trading rights with Japan in 1858 as a result of the efforts of __________, the American consul sent to Japan after the Treaty of Kanag
How did the Constitution overcome the weaknesses of the Articles of Confederation?
Why was the Reapportionment Act of 1929 passed?
Which character is not considered minor in The Tragedy of Julius Caesar? Lucius Messala Claudio Brutus
The process through which professional scientists evaluate the quality of each others’ research is called
Adolf Hitler flattered the German people by calling them the _______
Opium is a spice cherished by the Chinese. true or false
Which of these factors led to the stock market crash of 1929? high interest rates low tariff barriers high taxes excessive credit expansion
Which of the following is considered a xanthine? a. Acetylcysteine b. Guaifenesin c. Theophylline d. Epinephrine HCL
Who was Geoffrey Chaucer?