Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

under which of the following operations are the polynomials 8a 14 and 3b - 9 not closed? a. subtraction b. multiplication c. addition d. division
If h(X) = 2 —— 3+X Find: h(X-3)
Need help. Find the derivative of f(x) = 5x + 9 at x = 2. Find the derivative of f(x) = 6 divided by x at x = -2. Thanks
who was the first president of the united states?
Different ____________ are assigned to track multiple reviewers of a document. a. shapes c. colors b. numbers d. fonts
Factorise 2x^2+7x+12=0
which reason best explains why antibiotics do not work on viruses
what is the formula for the nth term of a geometric sequence with a4 = 16 and r =1/2 ?
type of weathering that occurs more rapidly in climates that experience frequent freezes and thaws
The purpose of the lady of shallot, a painting by Waterhouse, was to illustrate a/an