If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, how many containers are required?

Respuesta :

miamonroe56
miamonroe56 miamonroe56
  • 02-06-2017
5 times 100 = 500
500 divided by 20 = 25
25 containers
Answer Link

Otras preguntas

constant equality 123
I would like you _____ go _____the library _____ check out _____books each. I am going ____go _____, but I am going _____check out three, rather than____. Next
What would be the most appropriate initial investigation for thyroid nodules
Sequence: 1,5,13,25 Find nth term (Equation/formula thingy) Need answer ASAP
what is the full form of LAN​
Why does someone have any sensation below their shoulders?
Algebra 2 help please
On a coordinate plane, a right triangle has points A (negative 5, negative 6), B (negative 5, negative 2), C (negative 2, negative 2). Examine the right triangl
Which features are present in this polar graph?A. No symmetry B. Symmetry about the pole (0,0)C. Symmetry about the line Theta=pi/2D. Symmetry about the polar a
PLEASE HELP ME WITH THIS