In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

Use the distance formula to find the distance, to the nearest tenth, between each pair of pointsC (4,5) and D (0,2)
Find the equation that results from completing the square into the following equation X squared -14 X +40 equals zero
How do you figure out what the order pairs are in this equation? 2x-2=y
A mass falls from rest to the growl in 15 secs. Find y, the vertical distance it travelled
I need help expanding some log
Please help me solve this math question. Please explain each step clearly
Which of the following is/are true of the doing functions x2-169
Find the volume of thetriangular prism.24 m7 m3.6 mThe volume of the triangular prism ism3
A rectangle is placed around a as shown below. The length of the rectangle is 16 ft. Find the area of the shaded region Use the value 3.14 for aand do not round
I need help with this question could you review it