if 10 man can work 6hours.How many more men are needed towork in 4 hours​

Respuesta :

mathstudent55
mathstudent55 mathstudent55
  • 03-12-2021

Answer:

5 more men

Step-by-step explanation:

10 men do a job in 6 hours.

To do the job in 2 hours, 1/3 of the time, you need 3 times as many men.

30 men do a job in 2 hours.

To do the job in twice the time, 4 hours, you need half the men.

15 men do a job in 4 hours.

15 men - 10 men = 5 men

You need 5 more men.

Answer Link

Otras preguntas

Rita pumped 42 gallons of water into her pool. This was done over a period of 6 minutes at a constant Rate. What was the change in the amount of water in the po
Tony and Tiffany collect semi-precious stones. At the rock hound hut, Tiffany paid $38 for 9 pounds of snowflake obsidian. At the solid rock shop, tony paid $19
Please answer this asap! 20 POINTS :D
find the derivatives of the following implicit function
A company had a gross profit of $300,000 based on sales of $400,000. Its cost of goods sold equals $700,000 is this true or false?
Write the expression Divide y by 9 then subtract z from the result
What is the purpose of natural selection?​
WOULD LOVE IF SOMEONE CAN ANSWER THIS FOR ME, NEED HELP ASAP
A new car is purchased for 15100 dollars. The value of the car depreciates at 12.25% per year. To the nearest year, how long will it be until the value of the c
Find the equation of the line below. If necessary, use a slash (/) to indicate a division bar.