When looking at a program board at the end of program increment (PI) planning, what does it mean when a feature is placed in a team's swim lane with no strings

Respuesta :

IfeanyiEze8899 IfeanyiEze8899
  • 04-01-2021

Answer:

It simply means that other teams can independently complete the feature.

Explanation:

PI or program increment is a planning interval during which an agile release train (ART) plans and produces working and tested software and systems. It takes a duration of 8 to 12 weeks

Agile teams can access and independently complete various ARTs found in their swim lanes with no strings.

Answer Link

Otras preguntas

Use conversion tool to convert the binary numbers to decimal. 111001 1100000 1010101 1001000
The disruption of the cell cycle may lead to what
4) Which expression is equivalent to (-4x+3y-5)2 ? Select all that apply. 16y-10 16y10 10 16x-y-10 -83-5y?
why did speaker thousands of good wishes card and gift from all over the world?​
HELPPPPPP PLEASE Ezgi's mom took Ezgi and her five friends to the circus for her birthday party. Her mom got a $12.50 ticket and the same snack for each child f
Which of these statements is true about the Gentlemen's Agreement of 1907?
i need help plss help
sommme help ill give u 100 points
un resumen de la narración. “Tarde de agosto” de José Emilio Pacheco Plis daré coronita.
YEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEEAHHHH WHOOOOOOOO