Estimate the quantity of soil to be excavated from the borrow pit​

Respuesta :

lola2487
lola2487 lola2487
  • 04-08-2019

Answer

1056

Explanation:

for example

A soil is to be excavated from a borrow pit which has a density of 1.75g/cc and water content of 12%. The G is 2.7 the soil is compacted to that water content of 18% and dry density of 1.65g/cc. for 1000 m3 of soil used in fill estimate

Quantity of soil to be excavated from pit in m3

Answer Link

Otras preguntas

how do you balance __H2SO4 + __B(OH)3 --> __B2(SO4)3 + __H2O
Hey guys, I need 5 sentences!¿Prefieres viajar en coche, en tren, en barco o en avión? ¿Por qué?
how do you balance __H2SO4 + __B(OH)3 --> __B2(SO4)3 + __H2O
Hey guys, I need 5 sentences!¿Prefieres viajar en coche, en tren, en barco o en avión? ¿Por qué?
What are the advantages and disadvantages of globalization
how do you balance __H2SO4 + __B(OH)3 --> __B2(SO4)3 + __H2O
What are the advantages and disadvantages of globalization
Hey guys, I need 5 sentences!¿Prefieres viajar en coche, en tren, en barco o en avión? ¿Por qué?
how do you balance __H2SO4 + __B(OH)3 --> __B2(SO4)3 + __H2O
Hey guys, I need 5 sentences!¿Prefieres viajar en coche, en tren, en barco o en avión? ¿Por qué?